Financial Progress
Sl No.Name of the BlockOpening Balance as on 01.04.19Funds ReceivedOther Receipts (Interest etc)Total Funds available (Col. 3+4+5)Total Expenditure (in lakhs)Total Expenditure (in lakhs)Total Expenditure (in lakhs)Total Expenditure (in lakhs)Total Expenditure (in lakhs)
      BijiliSadakPANITotal (Col. 7+8+9 +10)%ge
1Jharsuguda72.170.000.0072.170.0018.720.0018.7225.94
2Kirmira14.900.000.0014.900.000.003.653.6524.50
3Kolabira27.420.000.0027.420.004.000.004.0014.59
4Laikera27.530.001.2928.820.000.000.000.000.00
5Lakhanpur16.10.000.0016.100.0010.000.0010.0062.11
 Total158.120.001.29159.410.0032.723.6536.3722.82
Physical Progress
Sl No.BlockBijliBijliBijliSadakSadakSadakPaniPaniPani
  Spillover projectsCompletion%Spillover projectsCompletion%Spillover projectsCompletion%
1Jharsuguda70054336115213
2Kirmira000211990232191
3Kolabira0004034859667
4Laikera944462518210770
5Lakhanpur151510022146413646
 Total31196119915176704260